May 12th, 2004 12:08 AM #1Guys,
Help naman kung sino na sa inyo ang naka kuha na ng building permit. Magkano ba at ilang araw bago makuha? sa San Pedro Laguna. At ano mga requirements sa pag aaply ng building permit?
Thanks
-
May 12th, 2004 01:59 AM #2
sir..
i came across your message, and as an architect/contractor, maybe i can help you and give you some tips re:building permit
it really depends on the structure, is it residential? commercial? industrial? but if its a residential project, you will be needing the following:
a. architecural plans
b. allied engineering plans (with seismic analysis if 3floors or more)
c. specifications of materials
d. soil testing result (optional)
e. bill of materials (estimates)
f. Lot documents or TCT
g. current lot tax declaration
h. application form for structural, electrical & sanitary permits, from your local government engineering office (sta.rosa)
i. for projects with medical related nature, you should also provide a clearance from the department of health, waste water clearance, etc.
the engineering office will determine the cost of the building permit by assessing your bill of materials. fire department permit should also be applied for.
normally, the contractor should be the one to apply for the permits in your behalf. if you need help in your project, please send me a PM..
i hope this helps..
rohan
-
May 12th, 2004 10:48 AM #3
dapat yun contractor na lahat gagawa niyan, including all other permit (sanitary, etc....)
-
May 12th, 2004 01:18 PM #4
kung ang balak mo naman eh ikaw ang mag-manage ng construction at wala ng contractor, then eto advice ko...
yung engineering plans pagawa mo dun sa engineer na nasa office mismo ng city engineer. guaranteed ang bilis ng release nyan! nasa "loob" na sya so lahat ng signatures na needed mo dyan eh pakisamahan na lnag sa kanila yan sa opis nila.
ganyan ginawa namin, twice na sa quezon city engineer's office. dali lang ma-release ng building permit.
-
Verified Tsikot Member
- Join Date
- Nov 2003
- Posts
- 64
May 12th, 2004 05:41 PM #5May engineering plan na kasi ko and then ako ang magmamanage ng construction para makatipid, residential lot sya at isa pa nyan iloloan ko sya, thru bank finance. Yong bang government eng'g office sa munisipyo mismo ba yon?
thanks sa reply.
-